PSM-I · Question #178
Which of the following are true about the length of the Sprint? (Choose two.)
The correct answer is B. It is best to have Sprints of consistent length throughout a development effort. E. All Sprints must be 1 month or less.. The correct answers are B and E, because these statements are true about the length of the Sprint. It is best to have Sprints of consistent length throughout a development effort, as this helps establish a reliable rhythm and cadence for the Scrum Team and the stakeholders. All S
Question
Which of the following are true about the length of the Sprint? (Choose two.)
Options
- AThe length of the Sprint should be proportional to the work that is done in between Sprints.
- BIt is best to have Sprints of consistent length throughout a development effort.
- CSprint length is determined during Sprint Planning, and should hold the time it will take to code
- DSprint length is determined during Sprint Planning, and should be long enough to make sure the
- EAll Sprints must be 1 month or less.
How the community answered
(44 responses)- A5% (2)
- B89% (39)
- C5% (2)
- D2% (1)
Explanation
The correct answers are B and E, because these statements are true about the length of the Sprint. It is best to have Sprints of consistent length throughout a development effort, as this helps establish a reliable rhythm and cadence for the Scrum Team and the stakeholders. All Sprints must be one month or less, as this ensures that the Scrum Team can inspect and adapt frequently and deliver value incrementally.
Topics
Community Discussion
No community discussion yet for this question.