nerdexam
ScrumScrum

PSM-I · Question #177

PSM-I Question #177: Real Exam Question with Answer & Explanation

The correct answer is B: The level of uncertainty over the technology to be used.. The correct answers are B and D, because the length of the Sprint should be chosen based on the level of uncertainty over the technology to be used and the risk of being disconnected from the stakeholders. The Scrum Guide states that "Sprints have consistent durations throughout

Submitted by alyssa_d· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

What two factors are best considered when establishing the Sprint length? (Choose two.)

Options

  • AThe organization has mandated similar length sprints.
  • BThe level of uncertainty over the technology to be used.
  • CThe frequency at which team formation can be changed.
  • DThe risk of being disconnected from the stakeholders.

Explanation

The correct answers are B and D, because the length of the Sprint should be chosen based on the level of uncertainty over the technology to be used and the risk of being disconnected from the stakeholders. The Scrum Guide states that "Sprints have consistent durations throughout a development effort. A new Sprint starts immediately after the conclusion of the previous Sprint. Sprints enable predictability by ensuring inspection and adaptation of progress toward a Sprint Goal at least every calendar month. When a Sprint's horizon is too long the Sprint Goal may become invalid, complexity may rise, and risk may increase."

Topics

#Sprint Length#Risk Mitigation#Uncertainty Management#Stakeholder Feedback

Community Discussion

No community discussion yet for this question.

Full PSM-I PracticeBrowse All PSM-I Questions