PSM-I · Question #179
PSM-I Question #179: Real Exam Question with Answer & Explanation
The correct answer is A: As soon as possible to minimize further deviation. Scrum's empirical framework is built on inspection and adaptation. When an inspection reveals that one or more aspects deviate outside acceptable limits, an adjustment must be made as soon as possible to minimize further deviation. This is a core Scrum principle — delaying adju
Question
If an inspector determines that one or more aspects of a process deviate outside acceptable limits, when must an adjustment be made?
Options
- AAs soon as possible to minimize further deviation
- BThe deviations should be discussed at the Daily Scrum and then an adjustment must be made
- CAfter clarifying all the details with the Product Owner
- DAfter Scrum Master approval
Explanation
Scrum's empirical framework is built on inspection and adaptation. When an inspection reveals that one or more aspects deviate outside acceptable limits, an adjustment must be made as soon as possible to minimize further deviation. This is a core Scrum principle — delaying adjustments allows problems to compound. Waiting for the Daily Scrum (B), consulting the Product Owner (C), or seeking Scrum Master approval (D) would introduce unnecessary delays. The Scrum Guide explicitly states that adjustments must be made 'as soon as possible' to keep the process or product on track.