nerdexam
Scrum

PSD · Question #9

What should the Scrum Team do during the first Sprint? (choose the best answer)

The correct answer is D. Create at least one valuable and useful Increment.. The first Sprint is focused on delivering a valuable and usable Increment. This embodies Scrum's iterative approach, where value is delivered early and feedback is gathered.

Applying Scrum

Question

What should the Scrum Team do during the first Sprint? (choose the best answer)

Options

  • AAnalyze, describe, and document the requirements for the subsequent Sprints.
  • BDefine the major product features and a release plan architecture.
  • CMake up a plan for the rest of the project.
  • DCreate at least one valuable and useful Increment.

How the community answered

(30 responses)
  • A
    7% (2)
  • C
    3% (1)
  • D
    90% (27)

Explanation

The first Sprint is focused on delivering a valuable and usable Increment. This embodies Scrum's iterative approach, where value is delivered early and feedback is gathered.

Topics

#first Sprint#usable Increment#Sprint Goal#Scrum fundamentals

Community Discussion

No community discussion yet for this question.

Full PSD Practice