PSD · Question #9
PSD Question #9: Real Exam Question with Answer & Explanation
The correct answer is D. Create at least one valuable and useful Increment.. The first Sprint is focused on delivering a valuable and usable Increment. This embodies Scrum's iterative approach, where value is delivered early and feedback is gathered.
Question
What should the Scrum Team do during the first Sprint? (choose the best answer)
Options
- AAnalyze, describe, and document the requirements for the subsequent Sprints.
- BDefine the major product features and a release plan architecture.
- CMake up a plan for the rest of the project.
- DCreate at least one valuable and useful Increment.
Explanation
The first Sprint is focused on delivering a valuable and usable Increment. This embodies Scrum's iterative approach, where value is delivered early and feedback is gathered.