When using Scrum, can a Scrum Team use Continuous Delivery? (choose the best answer)
The correct answer is E. Yes, there is nothing in Scrum that conflicts with Continuous Delivery.. Scrum is compatible with Continuous Delivery as long as each Increment meets the Definition of Done. Continuous Delivery aligns with Agile principles, allowing frequent releases.
Developing Products
Question
When using Scrum, can a Scrum Team use Continuous Delivery? (choose the best answer)
Options
- ANo, because the increment has to be approved at the Sprint Review before it can be released, and
- BNo, because stakeholders may have already seen the new features and the Sprint Review will be
- CNo, because before releasing an Increment it first has to fulfill the Definition of Done.
- DNo, because the Product Owner may not be available each time a PBI is done, and the Product
- EYes, there is nothing in Scrum that conflicts with Continuous Delivery.
How the community answered
(17 responses)- A6% (1)
- B6% (1)
- D18% (3)
- E71% (12)
Explanation
Scrum is compatible with Continuous Delivery as long as each Increment meets the Definition of Done. Continuous Delivery aligns with Agile principles, allowing frequent releases.
Topics
#Continuous Delivery#Scrum compatibility#Definition of Done#release cadence