Scrum
PSD · Question #11
When is refinement of a Product Backlog item complete? (choose the best answer)
The correct answer is C. When the Scrum Team agrees it is precise enough.. Refinement is complete when the Scrum Team agrees that the Product Backlog item is clear and precise enough to proceed with planning or implementation.
Applying Scrum
Question
When is refinement of a Product Backlog item complete? (choose the best answer)
Options
- AWhen the Product Owner says it is ready.
- BAt the end of Sprint Planning.
- CWhen the Scrum Team agrees it is precise enough.
- DWhen the Product Backlog Refinement timebox expires.
How the community answered
(30 responses)- A3% (1)
- B7% (2)
- C87% (26)
- D3% (1)
Explanation
Refinement is complete when the Scrum Team agrees that the Product Backlog item is clear and precise enough to proceed with planning or implementation.
Topics
#Product Backlog refinement#readiness criteria#Scrum Team consensus#backlog grooming