Scrum
PSD · Question #4
Developers are blocked by an impediment in the middle of the Sprint. The impediment is outside the Developer's control. What should they do? (choose the best answer)
The correct answer is B. Immediately raise the issue to the Scrum Master.. The Scrum Master is responsible for removing impediments. Developers should immediately raise the issue to the Scrum Master to facilitate resolution and maintain progress.
Applying Scrum
Question
Developers are blocked by an impediment in the middle of the Sprint. The impediment is outside the Developer's control. What should they do? (choose the best answer)
Options
- ACancel the Sprint.
- BImmediately raise the issue to the Scrum Master.
- CComplete the work that can be done and complete the remainder during the "hardening sprint".
- DStop using Scrum until the impediment is resolved.
- EDrop the Product Backlog items affected by the impediment from the Sprint Plan.
How the community answered
(53 responses)- B87% (46)
- C8% (4)
- D2% (1)
- E4% (2)
Explanation
The Scrum Master is responsible for removing impediments. Developers should immediately raise the issue to the Scrum Master to facilitate resolution and maintain progress.
Topics
#impediment removal#Scrum Master role#Sprint execution#Developer accountability