In what ways do Developers contribute to refining the Product Backlog? (choose the best three answers)

The correct answer is A. They may update estimates for Product Backlog items. C. They give input on technical dependencies. E. They ask QUESTIO N NO :s to clarify the intent of Product Backlog items.. Developers actively participate in Product Backlog refinement by updating estimates, identifying technical dependencies, and asking clarifying QUESTIO N NO :s to ensure shared

Applying Scrum

Question

In what ways do Developers contribute to refining the Product Backlog? (choose the best three answers)

Options

  • AThey may update estimates for Product Backlog items.
  • BThey do not. The Scrum Master and the Product Owner are responsible for Product Backlog
  • CThey give input on technical dependencies.
  • DThey do not. The Developers are only responsible for prioritizing technical work.
  • EThey ask QUESTIO N NO :s to clarify the intent of Product Backlog items.

How the community answered

(21 responses)
  • A
    95% (20)
  • D
    5% (1)

Explanation

Developers actively participate in Product Backlog refinement by updating estimates, identifying technical dependencies, and asking clarifying QUESTIO N NO :s to ensure shared

Topics

#Product Backlog refinement#Developer responsibilities#technical dependencies#estimation