nerdexam
Scrum

PSD · Question #39

When should a newly discovered huge bug of a previous sprint be fixed?

The correct answer is D. Depends on what the product owner wants.. Hiding the bug won't make it go away. Discussing with the product owner is a good step to take, because he knows what work leads to maximum value.

Applying Scrum

Question

When should a newly discovered huge bug of a previous sprint be fixed?

Options

  • AImmediately.
  • BDon't fix it immediately, but change the test to not show it as a temporary fix.
  • CDon't fix it, but stub out the code that causes it.
  • DDepends on what the product owner wants.

How the community answered

(13 responses)
  • A
    15% (2)
  • C
    8% (1)
  • D
    77% (10)

Explanation

Hiding the bug won't make it go away. Discussing with the product owner is a good step to take, because he knows what work leads to maximum value.

Topics

#bug prioritization#Product Owner decisions#Sprint Backlog management

Community Discussion

No community discussion yet for this question.