Scrum
PSD · Question #39
When should a newly discovered huge bug of a previous sprint be fixed?
The correct answer is D. Depends on what the product owner wants.. Hiding the bug won't make it go away. Discussing with the product owner is a good step to take, because he knows what work leads to maximum value.
Applying Scrum
Question
When should a newly discovered huge bug of a previous sprint be fixed?
Options
- AImmediately.
- BDon't fix it immediately, but change the test to not show it as a temporary fix.
- CDon't fix it, but stub out the code that causes it.
- DDepends on what the product owner wants.
How the community answered
(13 responses)- A15% (2)
- C8% (1)
- D77% (10)
Explanation
Hiding the bug won't make it go away. Discussing with the product owner is a good step to take, because he knows what work leads to maximum value.
Topics
#bug prioritization#Product Owner decisions#Sprint Backlog management