What happens if the Scrum Team cannot complete its work by the end of the Sprint? (choose the best answer)

The correct answer is B. The Sprint length is unchanged, and the Scrum Team continuously learns and adapts.. Scrum requires a fixed Sprint length. If work is incomplete, the team learns from it during the Sprint Retrospective and adjusts future planning and execution strategies.

Applying Scrum

Question

What happens if the Scrum Team cannot complete its work by the end of the Sprint? (choose the best answer)

Options

  • AThe Sprint is extended temporarily. Lessons are taken to ensure it does not happen again.
  • BThe Sprint length is unchanged, and the Scrum Team continuously learns and adapts.
  • CThe Sprint is extended, and future Sprints use this new duration.

How the community answered

(39 responses)
  • A
    8% (3)
  • B
    90% (35)
  • C
    3% (1)

Explanation

Scrum requires a fixed Sprint length. If work is incomplete, the team learns from it during the Sprint Retrospective and adjusts future planning and execution strategies.

Topics

#Sprint timebox#adaptation#incomplete work#Scrum Team