nerdexam
Scrum

PSD · Question #155

PSD Question #155: Real Exam Question with Answer & Explanation

The correct answer is A. Ready to be released to end users. C. No work is left to meet the Definition of Done.. An Increment is Done when it meets the Scrum Team's Definition of Done, ensuring that it is ready for release if required. It signifies no remaining work to meet quality and functionality

Question

A Scrum Team is required to deliver a Done Increment by the end of a Sprint. Select two statements that explain what Done means. (choose the best two answers)

Options

  • AReady to be released to end users.
  • BWhatever the Product Owner defines as quality.
  • CNo work is left to meet the Definition of Done.
  • DReady for integration.
  • EAll work the Developers are willing to do.

Explanation

An Increment is Done when it meets the Scrum Team's Definition of Done, ensuring that it is ready for release if required. It signifies no remaining work to meet quality and functionality

Community Discussion

No community discussion yet for this question.

Full PSD Practice