A Scrum Team is required to deliver a Done Increment by the end of a Sprint. Select two statements that explain what Done means. (choose the best two answers)

The correct answer is A. Ready to be released to end users. C. No work is left to meet the Definition of Done.. An Increment is Done when it meets the Scrum Team's Definition of Done, ensuring that it is ready for release if required. It signifies no remaining work to meet quality and functionality

Applying Scrum

Question

A Scrum Team is required to deliver a Done Increment by the end of a Sprint. Select two statements that explain what Done means. (choose the best two answers)

Options

  • AReady to be released to end users.
  • BWhatever the Product Owner defines as quality.
  • CNo work is left to meet the Definition of Done.
  • DReady for integration.
  • EAll work the Developers are willing to do.

How the community answered

(66 responses)
  • A
    88% (58)
  • B
    8% (5)
  • D
    3% (2)
  • E
    2% (1)

Explanation

An Increment is Done when it meets the Scrum Team's Definition of Done, ensuring that it is ready for release if required. It signifies no remaining work to meet quality and functionality

Topics

#Definition of Done#Increment#releasable#Sprint goal