Scrum
PSD · Question #122
How much time must a product owner spend with the developers?
The correct answer is A. However much time the developers ask the PO to be present. This should not be too much in a healthy situation, and this also doesn't imply that the developers can control the PO. But when the developers need the product owner to clarify or renegotiate the work to be done, it will be an impediment if the PO is not available.
Applying Scrum
Question
How much time must a product owner spend with the developers?
Options
- AHowever much time the developers ask the PO to be present
- B40%, or more depending on stakeholders
- C100%
- DEnough to be aware of the increment's value at the sprint review
How the community answered
(27 responses)- A89% (24)
- B7% (2)
- D4% (1)
Explanation
This should not be too much in a healthy situation, and this also doesn't imply that the developers can control the PO. But when the developers need the product owner to clarify or renegotiate the work to be done, it will be an impediment if the PO is not available.
Topics
#product owner role#collaboration#availability#sprint review