nerdexam
Scrum

PSD · Question #121

At the 10th sprint review, the stakeholders are disappointed and angry. They have determined that the product or system being built both will not meet their needs and will cost more than they are…

The correct answer is B. The product owner has not been keeping the stakeholders aware of the progress of the project D. The scrum master has not ensured that the project is transparent F. The stakeholders haven't been using sprint reviews to inspect and evaluate progress. there is no project plan, the presence of stakeholders in the development area is probably not helping and there is no project management. Transparancy would avoid the surprise for the stakeholders. If the PO didn't frequently update them, this can also lead to surprise and…

Applying Scrum

Question

At the 10th sprint review, the stakeholders are disappointed and angry. They have determined that the product or system being built both will not meet their needs and will cost more than they are willing to spend. What factors may have led to this? (choose three)

Options

  • AChanges to the project plan were not adequately documented and shared
  • BThe product owner has not been keeping the stakeholders aware of the progress of the project
  • CThe project management office has not been engaged adequately
  • DThe scrum master has not ensured that the project is transparent
  • EThe stakeholders were not allowed to enter the development area
  • FThe stakeholders haven't been using sprint reviews to inspect and evaluate progress

How the community answered

(35 responses)
  • A
    26% (9)
  • B
    54% (19)
  • C
    9% (3)
  • E
    11% (4)

Explanation

there is no project plan, the presence of stakeholders in the development area is probably not helping and there is no project management. Transparancy would avoid the surprise for the stakeholders. If the PO didn't frequently update them, this can also lead to surprise and disappointent. If the stakeholders couldn't attend the sprint review they would also not be up to date and missing out on an opportunity to inspect and adapt.

Topics

#sprint review#stakeholder engagement#transparency#product owner role

Community Discussion

No community discussion yet for this question.

Full PSD Practice