PMP · Question #1354
PMP Question #1354: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1354. The question stem and answer options stay visible for context.
Question
A team is testing a product on multiple radio frequencies. The project manager is informed that a new government policy, expected in 2 weeks, will mandate companies to obtain approval and licensing for frequency testing. The team has completed 80% of the testing and needs 4 weeks to complete the remaining tests. Which two actions should the project manager take until the approval is received? (Choose two.)
Options
- AHire a vendor with the required expertise and infrastructure to complete the testing.
- BStop testing immediately and escalate the issue to senior management for a decision.
- CAllow testing to continue for the complete duration as the policy may not apply to ongoing
- DUpdate the project risk checklist to consider licensing and approvals for risk identification.
- EReallocate the testing resources to complete testing early before the policy takes effect.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.