Question
A project sponsor is promoting the use of a new technology that has not yet been approved. The technology guarantees cost savings and a delivery ahead of schedule. However, the operational support at project completion is uncertain as the service organization expressed an inability to provide support without approval of the new technology. What should the project manager do to resolve the conflict?
Options
- ASeek to understand the project stakeholders' needs in an effort to support the new technology.
- BCommunicate the project's progress to the stakeholders and promote the new technology.
- CMaintain and adhere to project plans to ensure the project delivers successful outcomes.
- DAcknowledge the lack of approval and focus on a resolution that will benefit the customer.