PMIPMI
PMP · Question #978
PMP Question #978: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #978. The question stem and answer options stay visible for context.
Submitted by tyler.j· Apr 18, 2026Business Environment
Question
A project manager has recently been asked to take over an existing project that is halfway through execution. The project sponsor asked the project manager to ensure that the work carried out and the product being created do not deviate from the prescribed business value. What should the project manager do to achieve this goal?
Options
- AReview the requirements management plan.
- BMonitor the work breakdown structure (WBS).
- CCarry out quality audits and failure analyses.
- DReview the benefits realization plan.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Benefits Realization#Business Value#Strategic Alignment#Project Governance