nerdexam
PMIPMI

PMP · Question #87

PMP Question #87: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #87. The question stem and answer options stay visible for context.

Submitted by marco_it· Apr 18, 2026Business Environment

Question

A project manager has been assigned a project to build a new solar farm that will provide clean energy to a new housing complex. The government has decided to reduce the tax on renewable energy products starting 1 January. The supplier has reached out and stated that the order placed for solar panels to be delivered on 20 December might be delayed until early January. On the other hand, the project will face similar constraints due to the December holidays. What should the project manager do about this risk?

Options

  • AReview the supplier's contract to understand the terms of sale
  • BInsist that the supplier deliver the goods on the agreed date
  • CUpdate the risk register and take advantage of the opportunity
  • DAccept the risk and update the risk register

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Opportunity Management#Business Value#External Factors
Full PMP PracticeBrowse All PMP Questions