nerdexam
PMIPMI

PMP · Question #88

PMP Question #88: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #88. The question stem and answer options stay visible for context.

Submitted by yasin.bd· Apr 18, 2026Process

Question

A project manager is assigned to manage a project for a previous client of the company. The project manager was warned that this client will likely try to add extra scope to the project without considering the impact of change on time, cost, quality, and risks. Which action should the project manager take to help plan and manage the budget and resources?

Options

  • ARefuse to allow the client to change the scope and examine the lessons learned register.
  • BDecompose the deliverables into work packages and review the project charter.
  • CCreate tight scope statements and review the historical information.
  • DInclude a scope change process and review the project charter.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Scope Management#Change Management#Risk Management#Project Charter
Full PMP PracticeBrowse All PMP Questions