PMIPMI
PMP · Question #650
PMP Question #650: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #650. The question stem and answer options stay visible for context.
Submitted by stefanr· Apr 18, 2026Process
Question
A project sponsor would like to include a new deliverable. The sponsor contacts the project manager in order to seek advice on the most efficient approach to complete the deliverable within the next 2 months. What should the project manager do?
Options
- ASuggest that the sponsor conduct a cost-benefit analysis to determine feasibility.
- BAdvise the sponsor that it is not the project manager's job to evaluate the project.
- CUse the management reserve in order to expedite completion of the deliverable within 2 months.
- DChange the project methodology in order to achieve completion of the deliverable within 2
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Scope Management#Change Control#Project Reserves#Stakeholder Management