PMI
PMP · Question #921
A project manager is working on a project that is using a hybrid approach. One key input for the deliverable will be from the outcome of another project that is using an agile approach. What should th
Sign in or unlock PMP to reveal the answer and full explanation for question #921. The question stem and answer options stay visible for context.
Submitted by rachelw· Apr 18, 2026Process
Question
A project manager is working on a project that is using a hybrid approach. One key input for the deliverable will be from the outcome of another project that is using an agile approach. What should the project manager do next?
Options
- AParticipate in the other project's daily standup meetings.
- BAsk the other project manager to change the delivery methodology.
- CAlign with the other project manager's high-level project time lines.
- DRequest that the other project manager develop a work breakdown structure (WBS).
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Hybrid approach#Agile approach#Project dependencies#Schedule alignment