PMIPMI
PMP · Question #550
PMP Question #550: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #550. The question stem and answer options stay visible for context.
Submitted by suresh_in· Apr 18, 2026Process
Question
A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%. During the iteration retrospective, the team realizes that the complexity of the work was underestimated. What should the project manager do?
Options
- AUpdate the issue log and escalate it to the project sponsor.
- BAsk the technical manager to help the team with the issue.
- CMeet with the team to review internal actions to resolve the situation.
- DAsk to replace some team members with more experienced ones.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Agile Methodologies#Retrospective#Continuous Improvement#Estimation