PMP · Question #89

PMP Question #89: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #89. The question stem and answer options stay visible for context.

Submitted by tunde_lagos· Apr 18, 2026People

Question

A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis. The team member responds that they do not have the knowledge to perform such an analysis. What should the project manager do?

Options

  • AHelp the team member to perform the quantitative risk analysis through coaching, mentoring, and
  • BEscalate the issue to the functional manager
  • CPerform the quantitative risk analysis for the team member
  • DContact the project management office (PMO) and request them to assign another team member

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Team Development#Coaching and Mentoring#Skill Gaps
Full PMP PracticeBrowse All PMP Questions