Question
A project manager is appointed to manage an infrastructure project that spans across several countries, including different time zones within a subregion. It is likely that most of the project team members will never meet, but they will have to collaborate to ensure deliverables are met. What should the project manager do to ensure good collaboration between the remote project team members?
Options
- ADiscuss the concerns with the project sponsor and modify the project charter to include more
- BCreate a social media group platform for the team to create a supportive environment.
- CSet the ground rules and identify a contingency plan in the risk register.
- DPlan a communication method and allow the project team members to virtually interact.