PMI-SP · Question #260
PMI-SP Question #260: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-SP to reveal the answer and full explanation for question #260. The question stem and answer options stay visible for context.
Question
Andy is the project manager of the NHGQ project for his organization. He has elected to use a three-point estimate for his project. His project team, however, is complaining about participating in this estimate type because of the time it takes to predict the duration of activities. Andy, as the project manager, tells the project team that they must create the time estimate, as it will help this project and future similar projects. What is a three-point estimate?
Options
- AEach activity must be estimated for its optimistic, pessimistic, and most likely duration.
- BEach activity must be estimated for its optimistic, pessimistic, and most likely duration and
- CA three-point estimate, also known as PERT, uses the formula optimistic, plus four times the
- DA three-point estimate, also known as GERT, uses the formula optimistic, plus four times the
Unlock PMI-SP to see the answer
You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.