You are the project manager of the HGH Project. Thomas, your project sponsor, asked you to submit status reports every week, but now he wants you to submit the status reports every other week. What project management plan would you need to update to reflect this change from Thomas?
Options
- AScope management plan
- BPerformance management plan
- CCommunications management plan
- DProject management plan