PMI-SP · Question #234
PMI-SP Question #234: Real Exam Question with Answer & Explanation
The correct answer is C. Integrated change control. The integrated change control process reviews proposed changes and determines what effect the change will have on the entire project. This includes scope, time, cost, quality, human resources, communication, risk, and procurement. Integrated change control is a way to manage the
Question
Options
- AScope change control
- BSchedule change control
- CIntegrated change control
- DChange Control Board approval process
Explanation
The integrated change control process reviews proposed changes and determines what effect the change will have on the entire project. This includes scope, time, cost, quality, human resources, communication, risk, and procurement. Integrated change control is a way to manage the changes incurred during a project. It is a method that manages reviewing the suggestions for changes and utilizing the tools and techniques to evaluate whether the change should be approved or rejected. Integrated change control is a primary component of the project's change control system that examines the affect of a proposed change on the entire project. Answer option A is incorrect. Scope change control focuses only on the effect of the change on the Answer option B is incorrect. Schedule change control focuses only on the effect of the change on the schedule. Answer option D is incorrect. The Change Control Board is a committee of key stakeholders, usually management, the project manager, and the project customer, to evaluate proposed changes. This board, however, is not a project process.
Community Discussion
No community discussion yet for this question.