Harry works as a project manager for BlueWell Inc. He is determining the budget of the project. According to the PMBOK, there are seven inputs to this process. Which one of the following is NOT an…

The correct answer is B. Reserve analysis. Reserve analysis is not an input to the determine budget process. It is a technique used for determining the budget. The inputs to the determine budget process are as follows: Activity cost estimates Basis of estimates Scope baseline Project schedule Resource calendars…

Schedule Planning and Development

Question

Harry works as a project manager for BlueWell Inc. He is determining the budget of the project. According to the PMBOK, there are seven inputs to this process. Which one of the following is NOT an input to the determine budget process?

Options

  • AContract
  • BReserve analysis
  • CScope baseline
  • DProject schedule

How the community answered

(54 responses)
  • A
    4% (2)
  • B
    94% (51)
  • D
    2% (1)

Explanation

Reserve analysis is not an input to the determine budget process. It is a technique used for determining the budget. The inputs to the determine budget process are as follows: Activity cost estimates Basis of estimates Scope baseline Project schedule Resource calendars Contracts Organizational process assets

Topics

#determine budget#process inputs#reserve analysis#PMBOK