PMI-SP · Question #231
Harry works as a project manager for BlueWell Inc. He is determining the budget of the project. According to the PMBOK, there are seven inputs to this process. Which one of the following is NOT an…
The correct answer is B. Reserve analysis. Reserve analysis is not an input to the determine budget process. It is a technique used for determining the budget. The inputs to the determine budget process are as follows: Activity cost estimates Basis of estimates Scope baseline Project schedule Resource calendars…
Question
Harry works as a project manager for BlueWell Inc. He is determining the budget of the project. According to the PMBOK, there are seven inputs to this process. Which one of the following is NOT an input to the determine budget process?
Options
- AContract
- BReserve analysis
- CScope baseline
- DProject schedule
How the community answered
(54 responses)- A4% (2)
- B94% (51)
- D2% (1)
Explanation
Reserve analysis is not an input to the determine budget process. It is a technique used for determining the budget. The inputs to the determine budget process are as follows: Activity cost estimates Basis of estimates Scope baseline Project schedule Resource calendars Contracts Organizational process assets
Topics
Community Discussion
No community discussion yet for this question.