PMI
PMI-SP · Question #205
There are seven inputs to the estimate activity durations process. Which one of the following is NOT an input to this process?
Sign in or unlock PMI-SP to reveal the answer and full explanation for question #205. The question stem and answer options stay visible for context.
Schedule Planning and Development
Question
There are seven inputs to the estimate activity durations process. Which one of the following is NOT an input to this process?
Options
- AScope baseline
- BActivity attributes
- CActivity list
- DActivity resource requirements
Unlock PMI-SP to see the answer
You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#activity duration estimates#process inputs#activity list#activity attributes