nerdexam
PMI

PMI-SP · Question #205

There are seven inputs to the estimate activity durations process. Which one of the following is NOT an input to this process?

The correct answer is A. Scope baseline. The scope baseline is not an input to the estimate activity durations process. The project's scope statement is an input, but according to the PMBOK, the scope baseline is not. The seven inputs to this process are: activity list, activity attributes, activity resource…

Schedule Planning and Development

Question

There are seven inputs to the estimate activity durations process. Which one of the following is NOT an input to this process?

Options

  • AScope baseline
  • BActivity attributes
  • CActivity list
  • DActivity resource requirements

How the community answered

(28 responses)
  • A
    93% (26)
  • B
    4% (1)
  • C
    4% (1)

Explanation

The scope baseline is not an input to the estimate activity durations process. The project's scope statement is an input, but according to the PMBOK, the scope baseline is not. The seven inputs to this process are: activity list, activity attributes, activity resource requirements, resource calendars, project scope statement, enterprise environmental factors, and organizational process assets. Answer options C, B, and D are incorrect. These all are an input to the estimate activity durations process.

Topics

#activity duration estimates#process inputs#activity list#activity attributes

Community Discussion

No community discussion yet for this question.

Full PMI-SP Practice