PMI-SP · Question #204
PMI-SP Question #204: Real Exam Question with Answer & Explanation
The correct answer is D. Corrective action. Corrective actions include contingency plans and workaround plans, which are valid risk Answer option B is incorrect. The technical performance measurement may be part of the analysis of the risk, but not part of the response. Answer option A is incorrect. A risk audit may be app
Question
Options
- ARisk audit
- BTechnical performance measurement
- CEarned value management
- DCorrective action
Explanation
Corrective actions include contingency plans and workaround plans, which are valid risk Answer option B is incorrect. The technical performance measurement may be part of the analysis of the risk, but not part of the response. Answer option A is incorrect. A risk audit may be appropriate once the risk event and response has been identified. Answer option C is incorrect. The impact of the risk event may affect earned value management calculations, but EVM in and of itself is not a valid risk response.
Community Discussion
No community discussion yet for this question.