PMI-SP · Question #193

What schedule analysis simulation tool allows you, the project manager, to review possible combinations of events such as optimistic, most likely and pessimistic outcomes for your project?

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #193. The question stem and answer options stay visible for context.

Schedule Planning and Development

Question

What schedule analysis simulation tool allows you, the project manager, to review possible combinations of events such as optimistic, most likely and pessimistic outcomes for your project?

Options

  • APERT
  • BMonte Carlo
  • CPMIS
  • DGERT

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Monte Carlo simulation#schedule risk analysis#three-point estimates#what-if analysis