nerdexam
PMI

PMI-SP · Question #192

PMI-SP Question #192: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #192. The question stem and answer options stay visible for context.

Question

You work as the project manager for Blue Well Inc. You are working with your project team to schedule the days the project work will take place. You have created a project network diagram as shown in the figure: Based on this diagram, find out the earliest day on which Activity G can be started.

Exhibit

PMI-SP question #192 exhibit

Options

  • ADay 13
  • BDay 7
  • CDay 22
  • DDay 17

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PMI-SP Practice