PMI-SP · Question #192
You work as the project manager for Blue Well Inc. You are working with your project team to schedule the days the project work will take place. You have created a project network diagram as shown in
The correct answer is D. Day 17. The earliest Activity G can start is Day 17. This is because activities A, D, C, and F must all be completed before Activity G can start. Answer option A is incorrect. Day 13 does not account for Activity F since Activity F is also a predecessor to Activity G. Answer option C is
Question
You work as the project manager for Blue Well Inc. You are working with your project team to schedule the days the project work will take place. You have created a project network diagram as shown in the figure:
Based on this diagram, find out the earliest day on which Activity G can be started.
Exhibit
Options
- ADay 13
- BDay 7
- CDay 22
- DDay 17
How the community answered
(68 responses)- A19% (13)
- B4% (3)
- C9% (6)
- D68% (46)
Explanation
The earliest Activity G can start is Day 17. This is because activities A, D, C, and F must all be completed before Activity G can start. Answer option A is incorrect. Day 13 does not account for Activity F since Activity F is also a predecessor to Activity G. Answer option C is incorrect. Day 22 is the earliest Activity G can finish. Answer option B is incorrect. Day 7 is not a valid answer.