Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
The correct answer is B. Resource Leveling. You've hit your limit · resets 5am (America/New_York)
Schedule Planning and Development
Question
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
Options
- AApplying calendars
- BResource Leveling
- CResource Planning
- DResource Conflict Management
How the community answered
(32 responses)- B94% (30)
- C3% (1)
- D3% (1)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#resource leveling#critical path method#network analysis technique#resource availability