Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

The correct answer is B. Resource Leveling. You've hit your limit · resets 5am (America/New_York)

Schedule Planning and Development

Question

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

Options

  • AApplying calendars
  • BResource Leveling
  • CResource Planning
  • DResource Conflict Management

How the community answered

(32 responses)
  • B
    94% (30)
  • C
    3% (1)
  • D
    3% (1)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#resource leveling#critical path method#network analysis technique#resource availability