nerdexam
PMI

PMI-SP · Question #166

Which of the following outputs from the Schedule Control process aids in the communication of SV, SPI or any performance status to stakeholders?

The correct answer is C. Performance measurements. You've hit your limit · resets 5am (America/New_York)

Stakeholder Communication

Question

Which of the following outputs from the Schedule Control process aids in the communication of SV, SPI or any performance status to stakeholders?

Options

  • APerformance organizations
  • BSchedule baselines
  • CPerformance measurements
  • DChange requests

How the community answered

(33 responses)
  • B
    6% (2)
  • C
    91% (30)
  • D
    3% (1)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#performance measurements#schedule variance#SPI reporting#stakeholder reporting

Community Discussion

No community discussion yet for this question.

Full PMI-SP Practice