Which of the following outputs from the Schedule Control process aids in the communication of SV, SPI or any performance status to stakeholders?
The correct answer is C. Performance measurements. You've hit your limit · resets 5am (America/New_York)
Stakeholder Communication
Question
Which of the following outputs from the Schedule Control process aids in the communication of SV, SPI or any performance status to stakeholders?
Options
- APerformance organizations
- BSchedule baselines
- CPerformance measurements
- DChange requests
How the community answered
(33 responses)- B6% (2)
- C91% (30)
- D3% (1)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#performance measurements#schedule variance#SPI reporting#stakeholder reporting