nerdexam
PMIPMI

PMI-RMP · Question #89

PMI-RMP Question #89: Real Exam Question with Answer & Explanation

The correct answer is A: She can create an overall project rating scheme to reflect the bias towards risks that affect the. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

Amy is the project manager for her company. In her current project the organization has a very low tolerance for risk events that will affect the project schedule. Management has asked Amy to consider the affect of all the risks on the project schedule. What approach can Amy take to create a bias against risks that will affect the schedule of the project?

Options

  • AShe can create an overall project rating scheme to reflect the bias towards risks that affect the
  • BShe can filter all risks based on their affect on schedule versus other project objectives.
  • CShe can have the project team pad their time estimates to alleviate delays in the project schedule.
  • DShe can shift risk-laden activities that affect the project schedule from the critical path as much as

Topics

#Risk Assessment#Risk Tolerance#Qualitative Risk Analysis#Schedule Risk

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions