PMI-RMP · Question #87
You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. Which of the following inputs will be needed for the…
The correct answer is A. Organizational process assets C. Project scope statement D. Risk register. The standard PMBOK inputs to the Qualitative Risk Analysis process include: (A) Organizational process assets - historical data, lessons learned, and risk categories from past projects inform likelihood and impact assessments; (C) Project scope statement - helps determine how…
Question
You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. Which of the following inputs will be needed for the qualitative risk analysis process in your project? Each correct answer represents a complete solution. Choose all that apply.
Options
- AOrganizational process assets
- BCost management plan
- CProject scope statement
- DRisk register
How the community answered
(47 responses)- A91% (43)
- B9% (4)
Explanation
The standard PMBOK inputs to the Qualitative Risk Analysis process include: (A) Organizational process assets - historical data, lessons learned, and risk categories from past projects inform likelihood and impact assessments; (C) Project scope statement - helps determine how unique or complex the project is, which affects risk assessment; and (D) Risk register - contains the list of identified risks that need to be analyzed qualitatively. The cost management plan (B) is an input to cost-related processes but is not a standard input to Qualitative Risk Analysis, which focuses on probability and impact assessment rather than cost analysis.