The correct answer is A: Organizational process assets. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. Which of the following inputs will be needed for the qualitative risk analysis process in your project? Each correct answer represents a complete solution. Choose all that apply.

Options

  • AOrganizational process assets
  • BCost management plan
  • CProject scope statement
  • DRisk register

Topics

#Qualitative Risk Analysis#Risk Management Process#Project Inputs#Risk Register