PMI-RMP · Question #67

Ben is the project manager of the CMH Project for his organization. He has identified a risk that has a low probability of happening, but the impact of the risk event could save the project and the or

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #67. The question stem and answer options stay visible for context.

Risk Process Facilitation

Question

Ben is the project manager of the CMH Project for his organization. He has identified a risk that has a low probability of happening, but the impact of the risk event could save the project and the organization with a significant amount of capital. Ben assigns Laura to the risk event and instructs her to research the time, cost, and method to improve the probability of the positive risk event. Ben then communicates the risk event and response to management. What risk response has been used here?

Options

  • ASharing
  • BTransference
  • CEnhance
  • DExploit

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Positive Risk Response#Opportunity Management#Enhance Strategy#Risk Response Planning