PMI-RMP · Question #67
PMI-RMP Question #67: Real Exam Question with Answer & Explanation
The correct answer is C: Enhance. See the full explanation below for the reasoning.
Risk Process Facilitation
Question
Ben is the project manager of the CMH Project for his organization. He has identified a risk that has a low probability of happening, but the impact of the risk event could save the project and the organization with a significant amount of capital. Ben assigns Laura to the risk event and instructs her to research the time, cost, and method to improve the probability of the positive risk event. Ben then communicates the risk event and response to management. What risk response has been used here?
Options
- ASharing
- BTransference
- CEnhance
- DExploit
Topics
#Positive Risk Response#Opportunity Management#Enhance Strategy#Risk Response Planning