PMI-RMP · Question #634
PMI-RMP Question #634: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #634. The question stem and answer options stay visible for context.
Question
A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties. The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear. What should the risk manager advise the project manager?
Options
- AEscalate the new risks immediately to the project stakeholders to ensure proper risk
- BAddress these secondary risks as per the risk management plan
- CApply a risk acceptance strategy to the new risks as there is no risk response plan.
- DUpdate the risk management plan with the new probabily/impact and change the response.
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.