nerdexam
PMI

PMI-RMP · Question #62

You are the project manager of the GGK project for your company. The GGK project has a budget of $1,265,100 and is currently 40 percent complete. In this project, you elected to add labor to the proje

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #62. The question stem and answer options stay visible for context.

Risk Monitoring and Reporting

Question

You are the project manager of the GGK project for your company. The GGK project has a budget of $1,265,100 and is currently 40 percent complete. In this project, you elected to add labor to the project to increase the likelihood of completing the project early as the project was only scheduled to be 35 percent complete at this time. This positive risk response, while keeping the project ahead of schedule, has added significant costs to the project. You have already spent $575,000 to reach this point in the project. Management would like to know what your cost performance index and the schedule performance index is for this project. What are these values?

Options

  • AThe CPI is -$68,960 and the SPI is $63,255.
  • BThe CPI is .88 and the SPI is zero.
  • CThe CPI is .88 and the SPI is 1.14.
  • DThe CPI is 1.14 and the SPI is .88.

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Earned Value Management (EVM)#Cost Performance Index (CPI)#Schedule Performance Index (SPI)#Project Performance Reporting
Full PMI-RMP Practice