nerdexam
PMI

PMI-RMP · Question #602

The risk manager for an IT project developing a software application has a major stakeholder concerned that the project will not conclude within the available funding. The risk manager found delays in

The correct answer is D. Estimation and probability analysis tools (i.e. Monte Carlo simul-ations). Monte Carlo simulations and probabilistic estimation tools are specifically designed to model uncertainty in cost and schedule estimates by running thousands of scenario iterations, producing a probability distribution of possible outcomes. This allows the risk manager to quantif

Perform Targeted Risk Analysis

Question

The risk manager for an IT project developing a software application has a major stakeholder concerned that the project will not conclude within the available funding. The risk manager found delays in the iterations and increments in the project's budget, potentially increasing the duration by two weeks. What tools should the risk manager use to properly decide the risk of not finishing the project within the budget?

Options

  • AStakeholder management and communication tools
  • BTeam performance reports and analysis tools
  • CSchedule management tools (i.e., Gantt Charts)
  • DEstimation and probability analysis tools (i.e. Monte Carlo simul-ations)

How the community answered

(40 responses)
  • A
    3% (1)
  • B
    8% (3)
  • C
    5% (2)
  • D
    85% (34)

Explanation

Monte Carlo simulations and probabilistic estimation tools are specifically designed to model uncertainty in cost and schedule estimates by running thousands of scenario iterations, producing a probability distribution of possible outcomes. This allows the risk manager to quantify the likelihood of completing within the available budget given the identified delays. Stakeholder management and communication tools (A) facilitate information sharing but do not analyze financial risk. Team performance reports (B) describe past performance but do not forecast probabilistic outcomes. Gantt charts (C) visualize the schedule but do not provide probability-based cost risk analysis. Only estimation and probability analysis tools directly answer the question of whether the project will finish within budget, making D the correct choice.

Topics

#Quantitative Risk Analysis#Budget Risk#Monte Carlo Simulation#Risk Estimation

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice