PMI-RMP · Question #580
PMI-RMP Question #580: Real Exam Question with Answer & Explanation
The correct answer is C: Track identified risks and maintain the viability of response plans.. Monitoring risks during a project's lifecycle involves tracking identified risks and ensuring that response plans remain viable and effective. This continuous monitoring helps ensure that the project is prepared to address risks as they arise and that the risk response strategies
Question
During the project's lifecycle, project risk managers must monitor any risks and address risk responses. What does this level of monitoring consist of?
Options
- ACarry out the agreed risk response action should the risk occur.
- BProvide a numerical estimate of the overall effect of risk on the objectives.
- CTrack identified risks and maintain the viability of response plans.
- DDevelop the overall risk management strategy for risk integration.
Explanation
Monitoring risks during a project's lifecycle involves tracking identified risks and ensuring that response plans remain viable and effective. This continuous monitoring helps ensure that the project is prepared to address risks as they arise and that the risk response strategies remain appropriate as the project progresses. PMI guidelines stress the importance of ongoing risk monitoring to adapt to changes in the project environment and to ensure that the project remains on track to meet its objectives.