nerdexam
PMIPMI

PMI-RMP · Question #562

PMI-RMP Question #562: Real Exam Question with Answer & Explanation

The correct answer is D: Review the impact of the residual risk against the budget reserves and document the update in the. In risk management, when a residual risk is identified, it is crucial to reassess its impact on the project's overall risk profile. Residual risks are those risks that remain even after all mitigation strategies have been applied.

Risk Monitoring and Reporting

Question

The project manager reviews project risks with the risk manager to update, monitor, and close risks in the risk register. The project manager determines one of the risks has a residual risk. How should the risk manager document the impact of the residual risk?

Options

  • AUtilize change management tools to request a budget increase from the project sponsor and
  • BChange the risk identification and description on the risk register to reflect the fact that the residual
  • CClose the risk's status on the risk register since the residual risk has now materialized.
  • DReview the impact of the residual risk against the budget reserves and document the update in the

Explanation

In risk management, when a residual risk is identified, it is crucial to reassess its impact on the project's overall risk profile. Residual risks are those risks that remain even after all mitigation strategies have been applied.

Topics

#Residual risk#Risk register#Contingency reserves#Risk monitoring

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions