PMI-RMP · Question #561
During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team member
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #561. The question stem and answer options stay visible for context.
Question
During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team members do not agree that those risks can impact the project cost. What should the risk manager do to resolve the sponsor and project team members' concerns about risk identification?
Options
- AReinforce to the stakeholders that the risk identification was done properly during the last sprint.
- BHighlight the importance of agreeing on the risk identification to avoid further delays.
- CConduct a separate meeting to show the risk identification analysis to the stakeholders.
- DEnsure that the most knowledgeable members of the team validate risk identification processes.
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.