nerdexam
PMIPMI

PMI-RMP · Question #550

PMI-RMP Question #550: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #550. The question stem and answer options stay visible for context.

Risk Monitoring and Reporting

Question

A project manager for a predictive project just received a scope change request where additional development is required. What should the risk manager do to support the project manager with this scope change request?

Options

  • AEvaluate any new risks that are introduced due to the change in scope.
  • BUpdate the risk management plan to reflect the scope change.
  • CReassess the identified risks that impact the project scope.
  • DUpdate the risk register to identify, analyze, and plan a response for any new risk.

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk identification#Scope change impact#Predictive project#Risk management process
Full PMI-RMP PracticeBrowse All PMI-RMP Questions