PMI-RMP · Question #546
PMI-RMP Question #546: Real Exam Question with Answer & Explanation
The correct answer is A: Assess the identified secondary risk.. A secondary risk is a risk that arises as a direct result of implementing a risk response to a In this case, the risk response is to contract an external vendor to provide additional capacity and expertise to the project team. The secondary risk is the confidentiality risk that t
Question
An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register. What should the risk manager do next?
Options
- AAssess the identified secondary risk.
- BImplement the risk response plan.
- CImplement the risk contingency plan.
- DCommunicate the identified residual risk.
Explanation
A secondary risk is a risk that arises as a direct result of implementing a risk response to a In this case, the risk response is to contract an external vendor to provide additional capacity and expertise to the project team. The secondary risk is the confidentiality risk that the contracts department has identified. The risk manager should assess the secondary risk to determine its probability, impact, and priority, and to plan appropriate responses.
Topics
Community Discussion
No community discussion yet for this question.