Perform Targeted Risk Analysis

Question

A risk manager and relevant stakeholders have completed a risk response plan for a project. They have identified and planned responses to the known risks; however, a risk owner has identified and reported some residual risks not previously addressed. What should the risk manager do first?

Options

  • ADevelop a residual risk management plan to manage the residual risks.
  • BAnalyze, document, and communicate the residual risks to stakeholders.
  • CRecord the residual risks in the watch list for future reference.
  • DImplement the contingency plan when the residual risks occur.

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Residual risks#Risk analysis#Risk communication#Risk process
Full PMI-RMP PracticeBrowse All PMI-RMP Questions