PMI-RMP · Question #529

When selecting strategies as an activity of Plan Risk Response, what is the overall goal?

The correct answer is C. Select the strategies with the greatest overall positive influence. The overall goal of selecting strategies during the Plan Risk Response activity is to choose those strategies that have the greatest overall positive influence on the project, considering factors such as cost, schedule, and resources. One of the tasks in the domain of Risk…

Risk Strategy and Planning

Question

When selecting strategies as an activity of Plan Risk Response, what is the overall goal?

Options

  • ASelect the strategies with the least overall impact to resources.
  • BSelect the strategies with the least financial impact.
  • CSelect the strategies with the greatest overall positive influence.
  • DSelect the strategies with the greatest benefit to stakeholders.

How the community answered

(34 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    94% (32)

Explanation

The overall goal of selecting strategies during the Plan Risk Response activity is to choose those strategies that have the greatest overall positive influence on the project, considering factors such as cost, schedule, and resources. One of the tasks in the domain of Risk Response is to select risk response strategies based on the risk appetite and tolerance of the organization and stakeholders. The overall goal of selecting risk response strategies is to select the strategies with the greatest overall positive influence on the project objectives, such as scope, schedule, cost, quality, etc. The risk response strategies should aim to enhance the opportunities and reduce the threats to the project, while considering the cost- benefit analysis, the feasibility, and the alignment with the project goals and stakeholder expectations. The risk response strategies should not be selected based on the least overall impact to resources, because that may not be the most effective or efficient way to address the risks, and it may ignore the potential benefits of some strategies that may require more resources but also deliver more value. The risk response strategies should not be selected based on the least financial impact, because that may not be the most relevant or comprehensive criterion to evaluate the risks, and it may overlook other aspects of the project, such as quality, customer satisfaction, reputation, etc. that may also be affected by the risks. The risk response strategies should not be selected based on the greatest benefit to stakeholders, because that may not be the most realistic or achievable goal, and it may create conflicts or trade-offs among different stakeholder groups that may have different or competing interests, needs, and expectations5.

Topics

#Plan Risk Responses#Risk Response Strategies#Project Objectives#Risk Optimization