PMI-RMP · Question #512
A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project…
The correct answer is A. Develop an affinity diagram. An affinity diagram is a tool used to visually organize and group risks or ideas based on their similarities and categories. It helps in structuring the risks for further analysis and discussion. An affinity diagram is a tool and technique for the identify risks process that…
Question
A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop. What should the risk manager do next to visually organize the risks?
Options
- ADevelop an affinity diagram
- BPerform the analytical hierarchy process
- CPerform a SWOT analysis
- DAssign probability and impact
How the community answered
(30 responses)- A77% (23)
- B13% (4)
- C3% (1)
- D7% (2)
Explanation
An affinity diagram is a tool used to visually organize and group risks or ideas based on their similarities and categories. It helps in structuring the risks for further analysis and discussion. An affinity diagram is a tool and technique for the identify risks process that allows large numbers of ideas to be sorted into groups for review and analysis. An affinity diagram can help the risk manager to visually organize the risks identified in the pre- workshop survey by grouping them into categories based on their similarities or common characteristics. This can help the risk manager to facilitate the risk analysis and prioritization in the workshop, as well as to stimulate new patterns of thinking and generate additional risks.
Topics
Community Discussion
No community discussion yet for this question.