nerdexam
PMI

PMI-RMP · Question #508

When conducting a risk identification exercise, what two actions should the risk manager take? (Choose two.)

The correct answer is B. Arrange a team meeting, review the project's scope, and discuss dependency mapping D. Ensure that all the relevant stakeholders participate. Effective risk identification requires both the right process and the right participants. Arranging a team meeting, reviewing the project's scope, and discussing dependency mapping (B) provides the structured context needed to systematically uncover risks-scope review reveals wha

Risk Process Facilitation

Question

When conducting a risk identification exercise, what two actions should the risk manager take? (Choose two.)

Options

  • ARequest a contingency reserve from management
  • BArrange a team meeting, review the project's scope, and discuss dependency mapping
  • CEnsure participants review relevant documents before attending the meeting
  • DEnsure that all the relevant stakeholders participate
  • EUpdate the risk register during the team meeting.

How the community answered

(64 responses)
  • A
    9% (6)
  • B
    70% (45)
  • C
    17% (11)
  • E
    3% (2)

Explanation

Effective risk identification requires both the right process and the right participants. Arranging a team meeting, reviewing the project's scope, and discussing dependency mapping (B) provides the structured context needed to systematically uncover risks-scope review reveals what could go wrong, and dependency mapping exposes interdependency risks. Ensuring all relevant stakeholders participate (D) is critical because different stakeholders have different perspectives and knowledge areas; missing key participants means missing risks. Requesting a contingency reserve (A) is a risk response activity, not an identification activity. Ensuring pre-meeting document review (C) is a good practice but is not one of the two primary actions. Updating the risk register during the meeting (E) is premature-identification should be completed before updating formal documents.

Topics

#Risk Identification#Stakeholder Engagement#Meeting Facilitation#Project Scope Analysis

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice