PMI-RMP · Question #502
The project's customer has stated the project must be completed by a date indicated as the P90 date established on the Monte Carlo analysis. What should the project manager do to ensure the P90 date…
The correct answer is D. Mitigate risks identified on the sensitivity analysis. A P90 date from a Monte Carlo simulation means there is a 90% probability the project will finish by that date. To protect this high-confidence date, the project manager must reduce the threats most likely to push the schedule past it. Sensitivity analysis (often visualized as…
Question
The project's customer has stated the project must be completed by a date indicated as the P90 date established on the Monte Carlo analysis. What should the project manager do to ensure the P90 date is met?
Options
- AUpdate the assumptions/exclusions register
- BHire more resources and crash the schedule
- CPerform a qualitative risk analysis for the project
- DMitigate risks identified on the sensitivity analysis
How the community answered
(34 responses)- A6% (2)
- B9% (3)
- C15% (5)
- D71% (24)
Explanation
A P90 date from a Monte Carlo simulation means there is a 90% probability the project will finish by that date. To protect this high-confidence date, the project manager must reduce the threats most likely to push the schedule past it. Sensitivity analysis (often visualized as a tornado diagram) identifies which risks have the greatest impact on schedule variance-those are the ones to mitigate first. Option A (updating the assumptions register) is administrative and does not directly protect the date. Option B (crashing the schedule) is a cost-intensive technique not justified solely by a Monte Carlo result. Option C (qualitative risk analysis) has likely already been done and provides prioritization, not the targeted action needed to meet the P90 date.
Topics
Community Discussion
No community discussion yet for this question.