PMIPMI
PMI-RMP · Question #502
PMI-RMP Question #502: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #502. The question stem and answer options stay visible for context.
Perform Targeted Risk Analysis
Question
The project's customer has stated the project must be completed by a date indicated as the P90 date established on the Monte Carlo analysis. What should the project manager do to ensure the P90 date is met?
Options
- AUpdate the assumptions/exclusions register
- BHire more resources and crash the schedule
- CPerform a qualitative risk analysis for the project
- DMitigate risks identified on the sensitivity analysis
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Monte Carlo analysis#Quantitative risk analysis#Risk mitigation#Schedule risk management