nerdexam
PMI

PMI-RMP · Question #469

A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work. What is the project manager performing in this situatio

The correct answer is B. Risk transfer. By hiring a licensed contractor to complete the complex activity, the project manager is transferring the risk associated with that activity to the contractor. This is an example of risk transfer, as the responsibility for managing the risk is shifted from the project manager to

Risk Strategy and Planning

Question

A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work. What is the project manager performing in this situation?

Options

  • ARisk mitigation
  • BRisk transfer
  • CRisk acceptance
  • DRisk avoidance

How the community answered

(42 responses)
  • A
    7% (3)
  • B
    71% (30)
  • C
    17% (7)
  • D
    5% (2)

Explanation

By hiring a licensed contractor to complete the complex activity, the project manager is transferring the risk associated with that activity to the contractor. This is an example of risk transfer, as the responsibility for managing the risk is shifted from the project manager to the One of the domains of the PMI-RMP exam is Risk Response Planning, which involves developing options and actions to enhance opportunities and reduce threats to project objectives. One of the strategies for negative risks or threats is risk transfer, which involves shifting the impact of a threat to a third party, such as a contractor, a vendor, or an insurer. In this situation, the project manager is performing risk transfer by hiring a licensed contractor to complete the work that is too complex to complete internally. By doing so, the project manager is transferring the responsibility and liability of the activity to the contractor, who is expected to have the expertise and resources to handle the complexity. The project manager is not performing risk mitigation, which involves reducing the probability and/or impact of a threat. The project manager is not performing risk acceptance, which involves acknowledging the existence of a threat and making a conscious decision to accept it without taking any action. The project manager is not performing risk avoidance, which involves changing the project plan to eliminate the threat or protect the project objectives from its impact.

Topics

#Risk transfer#Threat response strategies#Procurement#Risk management

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice